• Company: An Environmental Engineering Consulting Firm
  • Category: Site Remediation & Restoration
  • Location: Detroit, MI
  • Focus: Remove a Leaking Underground Storage Tank and Contaminated Soil for an Environmental Engineering Consulting Firm.

Project Summary

  • ERG removed approximately 2,000 tons of impacted soil and materials.
  • The materials removed equates to approximately 50 truckloads of contaminated material.
  • A corresponding amount of clean fill needed to be brought to the site, put in place, and properly compacted to prevent future settling.

Project Tasks

  • Underground Storage Tank Removal
  • Removal of Contaminated Soil
  • Soil Transportation and Disposal
  • Tree removal and Landscaping
  • Site Remediation & Restoration
  • Removal of Concrete
  • Coordination of Subcontractors
  • Heavy Equipment Operation
  • Disposal of Petroleum Sludge and Residual Fuel.
  • Removal of miscellaneous site structures including a concrete & brick wall
  • Miscellaneous “extra” work-related items included Sidewalk Replacement and Traffic Control

Project Control

  • ERG completed the project quickly saved the client money.
  • ERG provided waste disposal manifests, supporting remediation documentation, and heavy equipment operation.
  • ERG obtained permits to shut down one lane of traffic to facilitate expedited load-out of contaminated soils.